top of page
Sanibel Logo.png

Update Tracker

Update Date
Title
Description
11/08/2025
Clubhouse
Flooring complete; framing in common area ongoing.
11/08/2025
Plumbing & Electrical Rough-In
Complete in F, G upper and lower.
11/08/2025
Framing
Complete in F, G lower; upper repairs ongoing.
11/08/2025
Landscaping
Materials delivered for A, B, C.
11/08/2025
Water Heaters
Installed in A–G; H in progress.
11/08/2025
Windows & Doors
Lower units complete; upper units ongoing A–H.
11/08/2025
HVAC
All rooftop and interior units installed.
11/08/2025
Bathrooms
Complete in A, B, C.
11/08/2025
Appliances
Installed in A, B; ordered for C–H.
11/08/2025
Kitchens
Cabinets and countertops done in A, B; C ongoing.
11/08/2025
Flooring
Complete in A, B, C; D, E next week.
11/08/2025
Painting
Exterior paint in progress on D, E, F.
11/08/2025
Stucco
Major stucco complete; minor repairs in progress.
11/08/2025
Electrical
All wiring and panels complete; clubhouse wiring ongoing.
10/30/2025
Windows
Slider Replacement has been completed in H8
10/30/2025
Windows
Replacement has been completed in H7
10/27/2025
Windows
Installation has begun in Building H
10/27/2025
Windows
Installation is complete in Buildings A, B, and C
10/27/2025
Sliding Doors
Installation has begun in Buildings A, B, and C
10/22/2025
Windows
2nd Floor Windows are Being Replaced for Impact Windows in all Buildings
10/22/2025
Exterior Panel
Has been installed on the Clubhouse
10/22/2025
Bathrooms
Toilets and vanities are currently being installed in Buildings A & B
10/13/2025
Windows
Installation beginning in Buildings A, B, & C
10/13/2025
Electrical
Installation Beginning in the Clubhouse Area
10/13/2025
Drywall
Installation Beginning in the Clubhouse Area
10/13/2025
Flooring
1/2 Completed in the Clubhouse Area
10/13/2025
Framing
Underway in the Clubhouse Area
10/13/2025
Exterior Pannels
Fully Installed and Ready for Inspection
09/29/2025
Storm Doors
Installation for Buildings A, B, & C to begin today.
09/29/2025
Windows
Installation for Buildings A, B, & C to begin today.
09/22/2025
Windows
Ordered and set to be delivered in two weeks for Buildings A, B, & C
09/22/2025
Landscaping
Materials delivered for installation in Buildings A & B
09/22/2025
Clubhouse Flooring
Underway in the storage side of building
09/22/2025
Bathrooms
Fully completed in Buildings A & B
09/22/2025
Flooring
Fully installed in Buildings A & B
09/22/2025
Doors & Trim
Fully installed in Buildings A & B
09/22/2025
Kitchen Cabinets
Fully installed in Buildings A & B
09/22/2025
Kitchen Countertops
Fully installed in Buildings A & B
09/15/2025
Kitchen Appliances
Currently being installed in Building A
09/15/2025
Kitchen Countertops
Currently being installed in Building A
09/10/2025
Exterior Painting
Underway at Buildings E & F
09/10/2025
Breaker Pannel Installation
Fully completed property wide besides Clubhouse
09/10/2025
AC Installation
Fully completed property wide besides Clubhouse
09/10/2025
Appliances
Have all been ordered for Buildings A & B
09/10/2025
Countertops
Currently being installed in Buildings A & B
09/10/2025
Trim
Currently being installed in Buildings A & B
09/10/2025
Doors
Currently being installed in Buildings A & B
09/10/2025
Kitchen Cabinets
Currently being installed in Buildings A & B
09/10/2025
Bathrooms
Currently being installed in Building A
09/10/2025
Flooring
Currently being installed in Building A
08/25/2025
Ceiling Framing
Commenced in Buildings F & G today
08/25/2025
Interior AC Installation
Still ongoing, will be completed in a week
08/25/2025
Exterior Painting
Buildings D&E have begun being painted
08/18/2025
AC Delivery
Fully delivered throughout all buildings
08/18/2025
Tankless Water Heaters
Fully delivered throughout all buildings
08/18/2025
Electrical Panels
Fully completed throughout all buildings
08/18/2025
Electrical Rough-Ins
Completed in all buildings except Building H
08/12/2025
AC Units
Buildings A,B,&C have each received the delivery of the AC units
08/12/2025
Stucco
All Stucco work has been completed site wide outside of minor patches
08/12/2025
Exterior Lighting
Initial surveying all day
08/05/2025
AC Installation
New AC units installed in top floor units of Buildings A and C. Building B has installed AC units on both floors.
08/05/2025
Underground Electrical Wiring
Fully completed across the property.
08/05/2025
Interior Electrical Panels 1/2
Installed in Buildings A, B, C, D, F, and G

Our Progress

Board of Directors

Our Location

TL_sanibel-island-aerial_HERO_SANIBEL0922-6d913093e0cb4e23a5dae21f97a93ad0.jpg

Have a Question or Concern About Your Unit?

Fill out all information below and we will contact you as soon as possible!

bottom of page