top of page
Sanibel Logo.png

Update Tracker

Update Date
Title
Description
11/25/2025
Building E – Units E1–E4
Electrical, plumbing, drywall, flooring complete; bathrooms partially complete.
11/25/2025
Building E – Exterior
Meter panels and roof repairs complete; exterior paint partially complete.
11/25/2025
Building E – Units E5–E8
Electrical upgrades and HVAC complete; tankless water heaters partially installed.
11/25/2025
Building G – Units G1–G4
Framing, electrical, plumbing, HVAC complete.
11/25/2025
Building D – Units D1–D4
Electrical, plumbing, drywall, flooring complete; bathrooms partially complete.
11/25/2025
Building H – Units H1–H4
Electrical, plumbing, drywall, flooring complete; bathrooms partially complete.
11/25/2025
Building A – Units A5–A8
Electrical upgrades and HVAC complete; drywall partially complete.
11/25/2025
Building C – Units C5–C8
Electrical and HVAC complete; drywall partially complete; tankless water heaters partially installed.
11/25/2025
Building H – Exterior
Meter panels and roof repairs complete
11/25/2025
Building G – Exterior
Roof coating, balconies, slabs, staircases complete; exterior paint remains in progress.
11/25/2025
Building H – Units H5–H8
Electrical upgrades, impact windows, HVAC complete.
11/25/2025
Building F – Units F1–F4
Framing, electrical, plumbing, HVAC complete.
11/25/2025
Building C – Units C1–C4
Electrical, plumbing, drywall, flooring complete
11/08/2025
Clubhouse
Flooring partially complete; framing continues in common area.
11/08/2025
Bathrooms
Complete in A; partial completion in B and C with remaining units outstanding.
11/08/2025
Water Heaters
Installed in select units A–G; partial installations remain in E, F, G; H in progress.
11/25/2025
Clubhouse – Exterior
Meter panels, HVAC units, and exterior primer paint complete.
11/25/2025
Clubhouse – Interior
Flooring fully installed and complete on storage side.
11/25/2025
Landscaping & Grounds
Materials ordered; debris removal and lawn maintenance ongoing.
11/25/2025
Boardwalk
Boardwalk framed; construction in progress.
11/25/2025
Pool
Pool resurfaced with plumbing complete; new pump and filter installed.
11/25/2025
Electrical & Utilities
Underground electrical complete property wide; LCEC conduits and transformers installed.
11/25/2025
Building G – Units G5–G8
Demolition, framing, MEP, insulation, and turtle glass impact windows installed.
11/25/2025
Building F – Exterior
Meter panels, balconies, second-floor slabs, staircases, and fire extinguishers complete.
11/25/2025
Building F – Units F5–F8
Demolition, framing, MEP, insulation, and turtle glass impact windows installed.
11/25/2025
Building D – Exterior
Meter panels, exterior paint, roof repairs, and roof coating complete.
11/25/2025
Building D – Units D5–D8
Electrical upgrades, impact windows, HVAC, tankless water heaters, drywall repairs complete.
11/25/2025
Building C – Exterior
Meter panels, exterior paint, roof repairs and coating, fascia, gutters, soffit complete.
11/25/2025
Building B – Exterior
Meter panels, exterior paint, roof repairs and coating, fascia, gutters, soffit complete.
11/25/2025
Building B – Units B5–B8
Electrical upgrades, impact windows, HVAC, tankless water heaters, drywall repairs, and finishes complete.
11/25/2025
Building B – Units B1–B4
All interior work complete including kitchens, bathrooms, flooring, finishes, HVAC, and tankless water heaters.
11/25/2025
Building A – Exterior
Meter panels, exterior paint, roof repairs and coating, fascia, gutters, soffit complete.
11/25/2025
Building A – Units A1–A4
All interior work complete including kitchens, bathrooms, flooring, finishes, HVAC, and tankless water heaters.
11/08/2025
Plumbing & Electrical Rough-In
Complete in F, G upper and lower.
11/08/2025
Framing
Complete in F, G lower; upper repairs ongoing.
11/08/2025
Landscaping
Materials delivered for A, B, C.
11/08/2025
Windows & Doors
Lower units complete; upper units ongoing A–H.
11/08/2025
HVAC
All rooftop and interior units installed.
11/08/2025
Appliances
Installed in A, B; ordered for C–H.
11/08/2025
Kitchens
Cabinets and countertops done in A, B; C ongoing.
11/08/2025
Flooring
Complete in A, B, C; D, E next week.
11/08/2025
Painting
Exterior paint in progress on D, E, F.
11/08/2025
Stucco
Major stucco complete; minor repairs in progress.
11/08/2025
Electrical
All wiring and panels complete; clubhouse wiring ongoing.
10/30/2025
Windows
Slider Replacement has been completed in H8
10/30/2025
Windows
Replacement has been completed in H7
10/27/2025
Windows
Installation has begun in Building H
10/27/2025
Windows
Installation is complete in Buildings A, B, and C
10/27/2025
Sliding Doors
Installation has begun in Buildings A, B, and C
10/22/2025
Windows
2nd Floor Windows are Being Replaced for Impact Windows in all Buildings
10/22/2025
Exterior Panel
Has been installed on the Clubhouse
10/22/2025
Bathrooms
Toilets and vanities are currently being installed in Buildings A & B
10/13/2025
Windows
Installation beginning in Buildings A, B, & C
10/13/2025
Electrical
Installation Beginning in the Clubhouse Area
10/13/2025
Drywall
Installation Beginning in the Clubhouse Area
10/13/2025
Flooring
1/2 Completed in the Clubhouse Area
10/13/2025
Framing
Underway in the Clubhouse Area
10/13/2025
Exterior Pannels
Fully Installed and Ready for Inspection
09/29/2025
Storm Doors
Installation for Buildings A, B, & C to begin today.
09/29/2025
Windows
Installation for Buildings A, B, & C to begin today.
09/22/2025
Windows
Ordered and set to be delivered in two weeks for Buildings A, B, & C
09/22/2025
Clubhouse Flooring
Underway in the storage side of building
09/22/2025
Bathrooms
Fully completed in Buildings A & B
09/22/2025
Flooring
Fully installed in Buildings A & B
09/22/2025
Doors & Trim
Fully installed in Buildings A & B
09/22/2025
Kitchen Cabinets
Fully installed in Buildings A & B
09/22/2025
Kitchen Countertops
Fully installed in Buildings A & B
09/15/2025
Kitchen Appliances
Currently being installed in Building A
09/15/2025
Kitchen Countertops
Currently being installed in Building A
09/10/2025
Exterior Painting
Underway at Buildings E & F
09/10/2025
Breaker Pannel Installation
Fully completed property wide besides Clubhouse
09/10/2025
AC Installation
Fully completed property wide besides Clubhouse
09/10/2025
Appliances
Have all been ordered for Buildings A & B
09/10/2025
Countertops
Currently being installed in Buildings A & B
09/10/2025
Trim
Currently being installed in Buildings A & B
09/10/2025
Doors
Currently being installed in Buildings A & B
09/10/2025
Kitchen Cabinets
Currently being installed in Buildings A & B
09/10/2025
Bathrooms
Currently being installed in Building A
09/10/2025
Flooring
Currently being installed in Building A
08/25/2025
Ceiling Framing
Commenced in Buildings F & G today
08/25/2025
Interior AC Installation
Still ongoing, will be completed in a week
08/25/2025
Exterior Painting
Buildings D&E have begun being painted
08/18/2025
AC Delivery
Fully delivered throughout all buildings
08/18/2025
Tankless Water Heaters
Fully delivered throughout all buildings
08/18/2025
Electrical Panels
Fully completed throughout all buildings
08/18/2025
Electrical Rough-Ins
Completed in all buildings except Building H
08/12/2025
AC Units
Buildings A,B,&C have each received the delivery of the AC units
08/12/2025
Stucco
All Stucco work has been completed site wide outside of minor patches
08/12/2025
Exterior Lighting
Initial surveying all day
08/05/2025
AC Installation
New AC units installed in top floor units of Buildings A and C. Building B has installed AC units on both floors.
08/05/2025
Underground Electrical Wiring
Fully completed across the property.
08/05/2025
Interior Electrical Panels 1/2
Installed in Buildings A, B, C, D, F, and G

Our Progress

Board of Directors

Our Location

TL_sanibel-island-aerial_HERO_SANIBEL0922-6d913093e0cb4e23a5dae21f97a93ad0.jpg

Have a Question or Concern About Your Unit?

Fill out all information below and we will contact you as soon as possible!

bottom of page