Sanibel Arms Reconstruction
Restoring the Heart of Sanibel Island Stronger, Safer, Sustainable.
Update Tracker
Update Date | Title | Description |
|---|---|---|
11/08/2025 | Clubhouse | Flooring complete; framing in common area ongoing. |
11/08/2025 | Plumbing & Electrical Rough-In | Complete in F, G upper and lower. |
11/08/2025 | Framing | Complete in F, G lower; upper repairs ongoing. |
11/08/2025 | Landscaping | Materials delivered for A, B, C. |
11/08/2025 | Water Heaters | Installed in A–G; H in progress. |
11/08/2025 | Windows & Doors | Lower units complete; upper units ongoing A–H. |
11/08/2025 | HVAC | All rooftop and interior units installed. |
11/08/2025 | Bathrooms | Complete in A, B, C. |
11/08/2025 | Appliances | Installed in A, B; ordered for C–H. |
11/08/2025 | Kitchens | Cabinets and countertops done in A, B; C ongoing. |
11/08/2025 | Flooring | Complete in A, B, C; D, E next week. |
11/08/2025 | Painting | Exterior paint in progress on D, E, F. |
11/08/2025 | Stucco | Major stucco complete; minor repairs in progress. |
11/08/2025 | Electrical | All wiring and panels complete; clubhouse wiring ongoing. |
10/30/2025 | Windows | Slider Replacement has been completed in H8 |
10/30/2025 | Windows | Replacement has been completed in H7 |
10/27/2025 | Windows | Installation has begun in Building H |
10/27/2025 | Windows | Installation is complete in Buildings A, B, and C |
10/27/2025 | Sliding Doors | Installation has begun in Buildings A, B, and C |
10/22/2025 | Windows | 2nd Floor Windows are Being Replaced for Impact Windows in all Buildings |
10/22/2025 | Exterior Panel | Has been installed on the Clubhouse |
10/22/2025 | Bathrooms | Toilets and vanities are currently being installed in Buildings A & B |
10/13/2025 | Windows | Installation beginning in Buildings A, B, & C |
10/13/2025 | Electrical | Installation Beginning in the Clubhouse Area |
10/13/2025 | Drywall | Installation Beginning in the Clubhouse Area |
10/13/2025 | Flooring | 1/2 Completed in the Clubhouse Area |
10/13/2025 | Framing | Underway in the Clubhouse Area |
10/13/2025 | Exterior Pannels | Fully Installed and Ready for Inspection |
09/29/2025 | Storm Doors | Installation for Buildings A, B, & C to begin today. |
09/29/2025 | Windows | Installation for Buildings A, B, & C to begin today. |
09/22/2025 | Windows | Ordered and set to be delivered in two weeks for Buildings A, B, & C |
09/22/2025 | Landscaping | Materials delivered for installation in Buildings A & B |
09/22/2025 | Clubhouse Flooring | Underway in the storage side of building |
09/22/2025 | Bathrooms | Fully completed in Buildings A & B |
09/22/2025 | Flooring | Fully installed in Buildings A & B |
09/22/2025 | Doors & Trim | Fully installed in Buildings A & B |
09/22/2025 | Kitchen Cabinets | Fully installed in Buildings A & B |
09/22/2025 | Kitchen Countertops | Fully installed in Buildings A & B |
09/15/2025 | Kitchen Appliances | Currently being installed in Building A |
09/15/2025 | Kitchen Countertops | Currently being installed in Building A |
09/10/2025 | Exterior Painting | Underway at Buildings E & F |
09/10/2025 | Breaker Pannel Installation | Fully completed property wide besides Clubhouse |
09/10/2025 | AC Installation | Fully completed property wide besides Clubhouse |
09/10/2025 | Appliances | Have all been ordered for Buildings A & B |
09/10/2025 | Countertops | Currently being installed in Buildings A & B |
09/10/2025 | Trim | Currently being installed in Buildings A & B |
09/10/2025 | Doors | Currently being installed in Buildings A & B |
09/10/2025 | Kitchen Cabinets | Currently being installed in Buildings A & B |
09/10/2025 | Bathrooms | Currently being installed in Building A |
09/10/2025 | Flooring | Currently being installed in Building A |
08/25/2025 | Ceiling Framing | Commenced in Buildings F & G today |
08/25/2025 | Interior AC Installation | Still ongoing, will be completed in a week |
08/25/2025 | Exterior Painting | Buildings D&E have begun being painted |
08/18/2025 | AC Delivery | Fully delivered throughout all buildings |
08/18/2025 | Tankless Water Heaters | Fully delivered throughout all buildings |
08/18/2025 | Electrical Panels | Fully completed throughout all buildings |
08/18/2025 | Electrical Rough-Ins | Completed in all buildings except Building H |
08/12/2025 | AC Units | Buildings A,B,&C have each received the delivery of the AC units |
08/12/2025 | Stucco | All Stucco work has been completed site wide outside of minor patches |
08/12/2025 | Exterior Lighting | Initial surveying all day |
08/05/2025 | AC Installation | New AC units installed in top floor units of Buildings A and C. Building B has installed AC units on both floors. |
08/05/2025 | Underground Electrical Wiring | Fully completed across the property. |
08/05/2025 | Interior Electrical Panels 1/2 | Installed in Buildings A, B, C, D, F, and G |